Location/Service Times Our Service About Us New Visitors
leftside
topline
Menu
toplineart
Homepage Heading
August 2010
The A/V (audio/visual) design is almost done. There will be a projection screen up front with a projector hidden behind the wall and a second screen on the back wall. A control center is planned on the left/rear side of the nave. The outside will have low maintenance materials.  The site will have new small plantings that are hardy and common to the New England area.  Detailed costs for all of these decisions are being collected and reviewed.  Some costs for optional systems such as air conditioning are now known.
July 2010
The detailed design is now focused on the roof design. It will be a combination of steel beams and wooden rafters.  The fire safety sprinkler system is being designed as well as the HVAC (heating and ventilation).  Windows and doors are next.
June 2010
Detailed Design drawings are continuing to be made with more details and options decided. A request has been made to the Mass Highway department to allow us to move our front access onto Route 28/Main Street ("curb cut").
May 2010
Great News! The town planning board and the town conservation committee have approved the site plan and the location of the new sanctuary (phase one). This means that they agree with the ways we plan to manage the storm water on the property, fire safety and other important items.  We still need to get a building permit but that will not be done until the design is complete and the construction costs are known. Detailed design drawings continue to be created and are being reviewed.
April 2010
The Design Drawings have progressed to the point where the committee and the Council want to review the progress and be sure that we are meeting our needs for phase one. The modified site plan has been submitted to the town and we will get a hearing in mid-May. The Planning board is also scheduled to met with us in May. If all goes well, we will be cleared to proceed. We also met with audio experts on the audio-visual needs.
March 2010
The modified site plan is complete and we are trying to schedule another meeting with the town to review and hopefully approve the plan. Once approval is obtained, other permitting can be requested.  While we wait, the architect has started the Design Drawings. These detailed drawings are used to develop a detailed cost for the construction. Decisions like doors, windows, siding are made in this phase.
February 2010
The peer review of the site plan was completed and it had some suggested changes to the design. These included some changes to drainage and the use of more native plants in the wetland areas. These changes are being incorporated into the site plan.
January 2010
A meeting was held with the town planning board to discuss the approval of the expansion of Faith Lutheran Church. The outcome was favorable but they still need to read the peer review report. That report is expected soon.
December 2009
Two meetings were held with the Town. The site plan was received favorably by the conservation commission with some suggestions for changes. The state DEP submitted some written concerns about the site design that they want the Town to address. The normal way to resolve these concerns is through a "peer" review where a second independent civil engineer reviews the plans and submits her  report. This is now taking place. Another meeting with the town is scheduled for January. We are also working to select a contractor partner to develop a buildable design within budget. We have decided to pursue a GMP contract with Murphy Construction of Newburyport, MA.

November 2009
A Notice of Intent to expand the facilities of Faith Lutheran Church was sent to the Town Of Andover. Several meetings with different boards will be required starting with two in December and more in January. Check the Town web page http://andoverma.gov/planning/ for dates of public hearings. We also need to involve the Commonwealth of Massachusetts because we plan to move the entrance to the church further south along Route 28. This meeting is not yet scheduled. The design continues to gain detail and engineering solutions.

October 2009
 The "neighbors" presentation was held where concerns were addressed and encouraging comments were received. Along with the site plan, this month, a landscape plan has been created that the town needs to approve. Because of the Thanksgiving holiday, our date(s) to present our plans to the town have been pushed into December. Fund raising continues.

September 2009
We have started the detailed design phase of the new sanctuary. This includes structural engineering, materials for construction, finishes and design of sub-systems like HVAC. We will be working closely with our general contractor to keep costs within budget and yet develop a structure we can be proud of.  Site engineering is mostly done and we next will contact the town to review and approve our plan.  We also notified "neighbors" about the new construction and invited them to a presentation.

August 2009
We have reached an agreement for the site engineering with Dana Perkins Civil Engineering. The next step after the engineering is done is to obtain approvals from the Town of Andover for the site.

July 2009
The BOF Committee is moving forward to create detailed design documents for the site and the phase one construction. Fund raising is also a major effort. Over half of the congregation has pledged or given funds already but we need to reach those that have been waiting for a final design concept.

June 2009
The Phase One Plan was approved by the Congregation at a special meeting.  Construction can begin when sufficient funds have been collected or pledged. The Congregation also approved a mortgage to help pay for the construction. Now the BOF committee is focusing its efforts on additional fund raising.

May 2009
The Phase One Plan was reviewed by a contractor and cost estimates for construction were within our proposed budget. Elevation views of the plan were made and the committee has asked the church council to call a Congregational Meeting (June 7th) to approve construction.

April 2009
The overall cost is still too high. The architect has proposed some cost cutting changes to the design for Phase One. The sanctuary was pushed back on the site to gain space and construction simplification, moved the mechanical room and simplified some other details. The next step is to get a cost estimate for construction.

March 2009
Costs of the new phase one effort are being itemized. This includes furnishings such as chairs, audio/visual needs, praise band needs and Christian Ed needs. A meeting with a representative of the ELCA Mission Investment Fund to discuss loan possibilities was held also.

February 2009
A schematic of the new phase one "stand alone" sanctuary was presented to the BOF committee this month. "Stand Alone" means no tearing down or modifications will be made to the existing building. Only a vestibule will connect the new sanctuary with the existing building. See these phase one outside views under "Views of New Building".

January 2009
The plans of the BOF committee were presented at the annual Congregation Meeting and interest in the project remains high in spite of the weak economy. To help close the gap between our resources and construction costs, the architect has proposed a new phase one plan that saves several hundreds of thousands of dollars. The details of that design are now being developed and views of it will be posted on the web next month.

December 2008
With the Advent and Christmas events at church, progress has slowed down. There are no new milestones to report.

November 2008
The BOF committee is meeting to work on replies to the concerns raised by the congregation after the presentations in October. An additional concern now is the weak economy. While it is a great time to build (lower costs), the giving potential of the church members needs reevaluation. Additional creative ways to fund the project are needed.

October 2008
The 3-D model and plans for the expansion were presented to the congregation in several gatherings. The plans were very well received and good questions were asked. Those questions of general interest or needing additional homework will be part of the FAQs section of the web and in printed materials to the congregation.

September 2008
The early site plan (Parking, drainage, roads, walkways, etc.) is complete but needs to be modified to meet our needs and budget. The BOF committee met with the Town of Andover officials and boards this month to "informally" present our plans. There was good discussion and suggestions made which we will make part of our formal proposal when we apply for permitting. The 3-D model of the new building is now available to view in the narthex of the church

August 2008
The schematic plan (concept) is more detailed now.  The wetlands have been defined by the civil engineer and a plan to handle storm water runoff is in the early design stage. A Three dimensional model of the new building plan, as developed so far, has been donated by Faith member, Craig Carlson's company, InDepth Design. Construction of this model is underway and will be available in September.

July 2008
Great progress has been made! We now have a plan with the sanctuary in the back of the property to avoid front setback issues and moved south to avoid the wetland setback concerns. We also have hired a civil engineer to work on the site plan, drainage and other issues.  The new sanctuary will have an entrance south of the existing entrance. Check out early views of the footprint here.

June 2008
Various options have been explored for the placement of the Sanctuary both for "traffic flow", visual impact and meeting town concerns. The plan to place the sanctuary out front requires town approval (variance) since it violates the front setback distance, the plan to place the sanctuary in the back violates the wetlands setback distance. Other placement options are being considered.

May 2008
The architects (Maugel, Architects http://www.maugel.com/ ) are in the schematic design phase. This means that they are designing the new spaces, reusing existing spaces and solving problems with location of important functions. They along with the"Building on Faith" or BOF committee need to secure Town of Andover approval for the new design.  The total cost for the project is only partially defined and there are some decisions that need to be made such as how close can we build to property lines and to the wetlands in the back of the property. Fund raising is continuing and the more we can raise the better off we are both in making these choices as well as reducing any need to take out a mortgage.


Home
About Us
Contact Us
Education
Expansion Project
Faith Weekly
Location/Service Times
Our Ministries
Coming Events

 
Footer
rightside